Soil excavation to its final depth has been completed throughout each section. Rebar installation has begun in the center section on top of the mud mat. Mud mat placement has occurred on the West side. Rebar installation has begun on the West side. Formwork is ongoing in the center section to prepare for the next concrete pour on 4/8. Excavation for site utilities has begun on the front side of the project site.