The slab-on-grade placements within the existing building are now complete, along with the majority of the lower-level slab-on-grade placements. The progress of the exterior sheathing and air vapor barrier surrounding the building and windows continues as well. Roofing installation has begun alongside the efforts for the mechanical, electrical, and plumbing work throughout all building floors. Within the existing building, penetrations have been made and lintels have been added for mechanical, electrical, and plumbing conduit. Utility tie-ins progress from Short Street to serve the new building.