The team continues to form and place concrete footings between the existing and new buildings. Foundation walls are being waterproofed, followed by install of foundation drainage and topped off with crushed stone. Underground plumbing installation is ongoing within the new concrete mat slab. The Learning Stairs are being formed and poured as the team works their way up to the existing building.