In the month of November, the Henry K. Oliver Project celebrated a significant milestone in the topping-off ceremony with the last steel beam being hoisted up into the building. The steel erection scope is now almost complete with final bolt connections and welds being finalized. Concrete decks have been poured in the lower floors of the east side of the building addition. The team is now working on tarping off and setting up temporary heating in that section of the addition in preparation for interior scopes of work. Additional work includes drainage connections at the intersection of Short and Oak Street.