The team continues to install framing and sheathing on the east side of the building addition progressing toward the west side along the exterior. Concrete placements continue throughout the new addition and are on track to be complete early this Spring. Installation of rough overhead mechanical, plumbing and electrical equipment continues throughout the new addition along with fireproofing at steel beams. In the existing building, excavation has been completed for the underground utilities and backfilling of these areas has begun.