The installation of exterior brick veneer, salvaged granite, exterior terracotta and metal paneling, and windows and curtainwalls are all ongoing. The team is also continuing to install ceiling grid framing, interior window trim and sills, ceramic wall and floor tile, interior partition drywall and finish, and first coat primer painting. Installation of the new roof system on the existing buildings has been progressing to ensure it is watertight. Installation of light fixtures has also begun and the main feeder cables from the main electrical room are being run throughout the building.